       Pembangunan Proyek MRT Capai 38 Persen

MRT Construction Reaches 38 Percent

The construction of Mass Rapid Transit (MRT) for south-north corridor phase 1 (Lebak Bulus - Bundaran HI) has reached 38 percent.

The overpass structure has reached 23 percent and 53 percent for underground

Dono Boestami, PT MRT Jakarta Director, ensured that the underground progress is escalating since October 2015.

“The overpass structure has reached 23 percent and 53 percent for underground,” he said, Tuesday (1/26).

Drilling for MRT Has Touched Senayan Station

At this moment, the project is working on construction for lane column and overpass station structure, underground station box structure, tunnel and depot construction.

“Please support us for this project runs well,” he added.

Linked News
Popular News indeks
  1. Closure of Railway Level Crossings Socialized

    access_time13-05-2026 remove_red_eye2370 personTiyo Surya Sakti
  2. Telkomsel Digiland Run 2026 Parking Lot List: Check Now!

    access_time14-05-2026 remove_red_eye990 personAldi Geri Lumban Tobing
  3. Governor Pram Appreciates Residents for Keeping Jakarta Safe and Comfortable

    access_time09-05-2026 remove_red_eye981 personFolmer
  4. Waste Sorting Movement Boosts Circular Economy

    access_time12-05-2026 remove_red_eye847 personFakhrizal Fakhri
  5. Fire Burns Five Houses in Cengkareng Extinguished

    access_time12-05-2026 remove_red_eye740 personBudhi Firmansyah Surapati