MRT Construction Reaches 38 Percent

The construction of Mass Rapid Transit (MRT) for south-north corridor phase 1 (Lebak Bulus - Bundaran HI) has reached 38 percent.

The overpass structure has reached 23 percent and 53 percent for underground

Dono Boestami, PT MRT Jakarta Director, ensured that the underground progress is escalating since October 2015.

“The overpass structure has reached 23 percent and 53 percent for underground,” he said, Tuesday (1/26).

Drilling for MRT Has Touched Senayan Station

At this moment, the project is working on construction for lane column and overpass station structure, underground station box structure, tunnel and depot construction.

“Please support us for this project runs well,” he added.

Linked News
Popular News indeks
  1. Rano: Pancasila is the Big House for Indonesia's Diversity

    access_time02-06-2025 remove_red_eye521 personBudhi Firmansyah Surapati
  2. Rano Requests PBSI to Hold Governor's Cup Championship

    access_time31-05-2025 remove_red_eye411 personBudhi Firmansyah Surapati
  3. Transjabodetabek Bogor–Blok M Route and Corridor 13 Extension Begin Operations

    access_time05-06-2025 remove_red_eye329 personDessy Suciati
  4. Friendly Countries' Ambassadors Participate in Famtrip to Seribu Islands

    access_time05-06-2025 remove_red_eye270 personAldi Geri Lumban Tobing
  5. No Odd-Even Restrictions in Jakarta on June 6-9, 2025

    access_time03-06-2025 remove_red_eye264 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik